Developer Not Liable for Delay If Construction Plea Is Kept Pending by Development Authority: Allahabad High Court

07 Jul 2025 3 min read
Developer Not Liable for Delay If Construction Plea Is Kept Pending by Development Authority: Allahabad High Court

In a significant judgment related to urban development and lease obligations, the Allahabad High Court has held that a developer cannot be penalized for not commencing construction when the application for construction permission is pending with the authority. The ruling came in the case of M/s Kinetic Buildtech Pvt. Ltd., which challenged the cancellation of its allotment by the Greater Noida Industrial Development Authority (GNIDA). Background of plot allotment and…

Read the full news in the Law4u app

Only today's news can be read in full on the website. This news is from 07 Jul 2025. Open it in the Law4u app, or in the Law4u web app on a computer, to read the complete story.

Read Full News
Don't have the app yet? Get it on Google Play or the App Store.

Latest News

View All

1M+

Downloads

Everything legal, in the Law4u app

Verified Advocates

Connect with vetted, verified lawyers

All Bar & State Acts

Every act, always up to date

Judgments

Search and read full judgments

Drafting

Ready legal drafts and templates

Constitution

The full Constitution, searchable

Daily Case Law

Fresh case law updates every day